Get the latest news about the Ohio Wetlands Foundation or just brush up on interesting facts about Ohio’s wetlands. Be sure to look at our useful links that include many resources for teachers and students studying wetlands.

OWF has compiled selected Ohio and Federal regulations governing wetlands and streams into a single, easy to use, pdf  document. DOWNLOAD your copy: 

January 2010 – SELECTED OHIO WETLANDS REGULATIONS.PDF

   

State of Ohio Regulations for Wetlands Permitting and Banking 

  • General State Isolated Wetlands Permit Level 1 Review (Category 1 or Category 2, one-half acre or less)
    • Time required for OEPA to determine application is complete = 15 days (6111.026)
    • Time required for a Level 1 review = 30 days (6111.022)
  • Individual State Isolated Wetlands Permit Level 2 Review (Category 1 greater than one-half acre or Category 2, greater than one-half acre but less than or equal to three acres)
    • Time required for OEPA to determine application is complete = 15 days (6111.026)
    • Time required for a Level 2 review = 90 days (6111.023)
    • Publish notice in newspaper, allowable time for comments and requests for public hearing = 20 days
    • If a public hearing is determined necessary, it must take place within 70 days after receipt of application.
  • Individual State Isolated Wetlands Permit Level 3 Review (Category 2 greater than three acres or a Category 3)
    • Time required for OEPA to determine application is complete = 15 days (6111.026)
    • Time required for a Level 3 review = 180 days (6111.024)
  • OAC Chapter 3745-1 Water Quality Standards
  • OAC Chapter 3745-32 Section 401 Water Quality Certifications

 Federal Regulations for Wetlands Permitting and Banking

  • Section 404 of the Clean Water Act
  • Individual 404 Permit
    • Time required for USACE to determine application is complete = 15 days (33CFR 325.2(a)(2))
    • Time
  • Nationwide Permits
    • NWP29 – Residential Developments (wetlands one-half acre or less, streams 300 feet or less)
    • NWP39 – Commercial Developments (wetlands one-half acre or less, streams 300 feet or less)
  • Final Compensatory Mitigation Rule